First Projects/Timeline (Year One)

HVAC improvements

  • Capital High School - KCS hopes to be out to bid by the end of 2019 on this project, which is anticipated to take two years due to the size of the school and age of the current system and level of needed updates.

  • George Washington High School - KCS hopes to be out to bid by the end of 2019 on this project, which is anticipated to take one year to complete.

  • Alum Creek Elementary - project accepted by SBA - anticipated start, Spring of 2020.

Roofing Projects

  • Capital High School - project movement will start in at the same time as the HVAC project and run concurrently with the HVAC repairs.

  • Other smaller schools will be added once we understand better the amount of funding.

Athletic Turf Installation

  • Sissonville High School - project completed September 2019.

  • Riverside High School - project completed September 2019.

  • The other 5 high schools included in the excess levy will see project movement in Spring 2020, thanks to savings from financing the project.

  • The Capital High School soccer field has been included in the financing package and will be included as part of the larger project as ballot projects are completed.

If you have any specific questions, please e-mail levy@mail.kana.k12.wv.us. Thank you.