Current Projects (Updated 6/25/21)

HVAC improvements

  • Capital High School - Building A, the academic wing, is mostly complete with new ceiling and LED light fixtures.  Work progressing in Building B.  All HVAC units are installed and the roof is approximately 99% complete.  Work will continue on Building B throughout the school year and summer of 2021.

  • George Washington High School - Work continues on installation of new ductwork above main level and thru second floor.  The ductwork on roof has been installed.  Ceiling and light fixture installation in main corridor, commons and corridor in front of offices has been completed.  Aux Gym unit has been installed but not connected.  Demolition continues on second floor.  Work will continue throughout the school year. 
  • Dunbar Middle School - The geothermal well field has been drilled and the piping loops are installed.  Demolition continues on the existing systems where possible and ductwork has been installed.  The phase 1 of the roofing project is complete. New ceilings are being installed with new LED lighting.  
  • Alum Creek Elementary - The Annex renovation is nearly complete and is expected to be turned over to the school in March.  The addition walls and roof are complete with interior electrical, mechanical work continuing.  
  • Elk Elementary Center - Geothermal well field drilling has commenced.  LED light retrofits are being installed.  HVAC /Mechanical has begun.
  • Lakewood Elementary - Equipment and materials are ordered and work is expected to commence in March.
  • St. Albans High School - LED light retrofits are installed and equipment is ordered. HVAC/Mechanical work and commenced.  

Roofing Projects

  • Capital High School - the roof is 99% complete.

  • Dunbar Middle - Phase 1 of the roof project is complete.

  • Completed levy roof projects:

    • Pratt Elementary
    • Malden Elementary
    • Sharon Dawes Elementary
    • Ruthlawn Elementary
    • McKinley Middle School
    • Belle Elementary
    • Pinch Elementary
    • Nitro High School - expected to begins when weather permits.

Schedule of Future Roof/HVAC Projects: 

Summer 2021

Nitro High - Roof

Dunbar Middle - Phase 2 Roof

Dunbar Middle - HVAC

St Albans High - HVAC

Elk Elementary - HVAC

Lakewood Elementary - HVAC

Summer 2022

Carver Career - HVAC & Roof

Grandview Elementary - HVAC & Roof

Riverside High - HVAC & Roof

Kanawha City Elementary - HVAC

West Side Middle - HVAC

Summer 2023

Sissonville High - HVAC

South Charleston High - HVAC

 

 Athletic Turf Installation

  • All complete!

Safety & Security

  • Intruder lock sets on all county-wide school building doors that did not previously have them. Complete.
  • Year 2 - in progress - access control software/driver's license scanner upgrade along with an emergency radio system (base radio) upgrade.

If you have any specific questions, please e-mail levy@mail.kana.k12.wv.us. Thank you.