Cedar Grove Renovation

Work is underway on the demolition of old portions of the Cedar Grove Community School, allowing for the renovation of Cedar Grove Elementary School. This is a School Building Authority (SBA) / KCS - funded project. 

9-20-24

The new gym floor has been installed and work continues on the new administrative wing. 

CGE new gym

CGE admin wing

7-31-24

The newest progress includes: installation of the new parent pick up road, the installation of the PreK playground, the multi-purpose room being primed for paint, progress on the new administrative area block work, and the new outdoor classroom being prepped for concrete to be poured. 

CGES Parent Pickup

CGES PreK playground

CGES footers for admin wing

7-9-24

Work continues on the brick veneer, roof and HVAC for the PE classroom. The foundation has been laid for the new administrative office section of the school. Crews are starting on the outdoor classroom.

CGE Admin Building

Admin footer

5-10-24

Work will continue over the summer on exterior updates and the new administrative offices.

CGE May Update

CGE Update May

CGE Update May

CGE May UPdate

2-5-24

  • Continuing work on 1st floor, flooring and ceiling being installed 
  • Paint crew has started on 1st floor 
  • First floor window installation ongoing 
  •  6 of 57 piers have been drilled, and concrete foundation has begun 
  • Crew pouring temporary sidewalk from cafeteria to dumpsters 

1st floor classroom progress 

CGES First Floor

11-29-23

Students were welcomed into the new 2nd floor classrooms coming back Monday from Thanksgiving break! The new space is beautiful and students/staff are thrilled.

CGES Library

CGES Library

CGES 2nd Floor Class

CGES 2nd Floor Class

10-20-23

New rooftop equipment has been set. Electrical contractors are working to make final pulls to the 2nd floor. Controls contractors are working to complete 2nd floor programming. Planning is underway to move 2nd-5th graders in in about a month!

CGES rooftop

9-21-23

The second floor is 96% complete. Ceiling work is continuing in the 2nd floor main corridor. Casework, walls, and furniture have been assembled and installed. Work is continuing on the first floor and is in phase 2.

CGES 2nd Floor

CGES 1st Floor

8-24-23

The school opened to students on Friday, Aug. 18th with ongoing construction.

Progress is being made daily. A temporary playground was installed and fenced in. All temporary classrooms are in place. They are laying flooring on the 2nd floor. 

CGES Upstairs

CGES Upstairs

CGES Upstairs cabinets

7-5-23

Second floor demolition is complete. Second floor masonry entryways and divider stud walls are being installed. Second floor HVAC and electrical rough-in are complete. First floor demo is underway. Project is on schedule. 

CGES Outside

CGES Inside

5-17-23

Asbestos abatement has been completed on the gym. Demolition of the gym has resumed. Hydronic piping is being installed on the 2nd floor.

CGES gym demo

5-3-23

The pod and theater demolition is complete. Demo is underway on the gymnasium. HVAC, electrical, and masonry demo/install is ongoing.

CGES demo

4-27-23

Continued work includes the demolition of the theater. 

Cedar Grove Demo

4-19-23

The Pod which housed the PreK-2nd Grades is completely down and the area has been seeded. The contractor has begun on the second floor of the building.

Outside CGES

CGES Outside

CGES Outside

Inside CGES Work

3-31-23

The Pod which housed the PreK-2nd Grades is almost down. The contractor has begun on the second floor of the building.

The demolition contractor will start demolition of the gym in approximately two weeks. The General Contractor has begun minor demolition of the second floor and is constructing temporary partitions.

CGES Outside

CGES Outside

CGES Inside

Website by SchoolMessenger Presence. © 2024 SchoolMessenger Corporation. All rights reserved.