Current Projects (Updated 12/16/20)

HVAC improvements

  • Capital High School - Building A, the academic wing, is mostly complete with work progressing in Building B. All HVAC units are onsite and the roof is approximately 99% complete. Work will continue on Building B throughout the school year and summer of 2021.

  • George Washington High School - Work on the lower level classrooms space is mostly complete. The Geothermal well field has been installed and the parking lot repaved. Work in the band room and locker room areas of the facility is nearly complete as well as the kitchen area. Work will continue this school year throughout the facility. 

  • Dunbar Middle School - The Geothermal well field has been drilled and the piping loops are installed.  Demolition continues on the existing systems where possible and ductwork is being installed. The phase 1 of the roofing project is complete.

  • Alum Creek Elementary - The floor slabs for the new administration suite are installed.  The block walls are complete with the structural steel scheduled to arrive next week.  The Annex work is on schedule and is scheduled to be completed by mid-February, 2021.

  • Engineering is complete and bids have been received for the following future projects: Elk Elementary Center, Lakewood Elementary, St. Albans HS, Carver, Grandview, Riverside HS, Piedmont Elementary, Kanawha City Elementary, West Side Middle, Sissonville HS & South Charleston HS. 

Roofing Projects

  • Capital High School - the roof is 99% complete.

  • Dunbar Middle - Phase 1 of the roof project is complete.

  • Completed roofs: Pratt Elementary, Malden Elementary, Sharon Dawes Elementary, Ruthlawn Elementary & McKinley Middle

  • In progress and nearing completion at: Pinch, Belle and Montrose Elementary.

  • Architectural and engineering complete or nearly complete for future projects: Carver, Grandview, Riverside, Nitro HS

  • Future roofing project - DuPont Middle - goes to Board for approval on Dec. 17, 2020. Cedar Grove - preliminary design sketches being completed. 

Athletic Turf Installation

  • All complete!

Safety & Security

  • Intruder lock sets on all county-wide school building doors that did not previously have them. Complete.
  • Year 2 - in progress - access control software/driver's license scanner upgrade along with an emergency radio system (base radio) upgrade.

If you have any specific questions, please e-mail levy@mail.kana.k12.wv.us. Thank you.